Timeline of Activity
Consultation is an essential part of the Essex LNRS. Here are some of the key dates in that process of information sharing and gathering.
March 2023
- DEFRA releases regulations and guidelines
April – May 2023
- LNRS working group meetings.
- Meeting with Supporting Authorities (SAs).
- Review existing plans and strategies across Essex.
June – July 2023
- Subgroup meetings begin.
- Stakeholder engagement implemented and agreed.
- Begin drafting biodiversity priorities/strategy.
- Feedback on LNRS progress from LNP board.
August 2023
- Ground Control commence mapping work on the Local Habitat Map.
- Regular meetings with Supporting Authorities.
- Sector specific subgroup meetings.
- Habitat and species specific subgroup meetings.
- Processing and integrating feedback, advice and guidance from these meetings into the strategy.
September 2023
- Local Habitat Map (LHM): ‘areas of particular importance for biodiversity’ data layer completed by Ground Control.
- KAT Marketing join core LNRS delivery team to support with wider engagement on the LNRS.
- Ground Control lead mapping subgroup meetings. Opportunity mapping analysis models are discussed.
October 2023
- LNP Board Meeting at the end of October, focusing on the LNRS.
- Wider stakeholder engagement planning continues.
- Engagement plan produced.
November 2023
- Stakeholder engagement throughout November.
- LNRS strategy content continued to be drafted. LNRS engagement webinars and workshops took place and feedback was incorporated into the draft strategy.
December 2023
- LNRS mapping work progresses.
- Engagement with stakeholders and specialist subgroups continues.
January 2024
- Farmers and landowners workshop to take place.
- LNRS drafting progresses.
- LNRS draft shared with Local Nature Partnership board for their initial review.
- Mapping approaches developed as result of workshops.
February 2024
- Local Nature Partnership board provide feedback on LNRS initial draft.
- Feedback is reviewed and LNRS drafting continues, with the support of the LNRS working group, subgroups and mapping group.
March – May 2024
- Wider engagement with landowners, farmers, local communities and new audiences continues.
- Final preparations are made to the LNRS draft ahead of internal Essex County Council governance processes.
- 1-2-1 meeting with Supporting Authorities.
- Preparation for LNRS Supporting Authority consultation launch
- Launch of Supporting Authority Consultation for 28 days.
June 2024
- Launch of Supporting Authority Consultation for 28 days.
July 2024
- Consultation with Supporting Authorities closes.
- Feedback reviewed from Supporting Authorities.
- LNRS draft prepared for public consultation.
- Wider engagement continues with members of the public, land agents, community groups.
August 2024
- Launch of Public Consultation on 30 August for 8 weeks.
September 2024
Public consultation continues throughout this month.
October 2024
- Public Consultation Closed on 25 October 2024.
November – December 2024
- All Public Consultation feedback reviewed and actioned.
2025 and beyond…
- Public Consultation feedback continues to be actioned into 2025.
- Consultation with Supporting Authorities.
- Final draft reviewed.
- Essex County Council governance processes.
- Publication of LNRS.
- Implementation and delivery of the LNRS.
Delivery Structure